Interactive model

Where does the water go?

Joat Ville loses half of the water it puts into supply. Find the faults, apply the fix, and watch Non Revenue Water fall in real time.

An illustrative model of a typical municipal distribution system. Figures follow the standard IWA water balance and are used to explain the method, not to report a specific project result.

Non Revenue Water80 639 kl/day
50,0%
Baseline
Real losses
59 840kl/day
Leaks, bursts and overflows
Apparent losses
7 803kl/day
Meter error and illegal use
Water recovered
0kl/day
Nothing recovered yet
RuralPeri UrbanCBDResidentialIndustrialJoat Ville ReservoirInteractive Water Loss Model | JOATInteractive Water Loss Model | JOATInteractive Water Loss Model | JOATInteractive Water Loss Model | JOATInteractive Water Loss Model | JOATInteractive Water Loss Model | JOATInteractive Water Loss Model | JOATInteractive Water Loss Model | JOATInteractive Water Loss Model | JOATInteractive Water Loss Model | JOATInteractive Water Loss Model | JOATInteractive Water Loss Model | JOATInteractive Water Loss Model | JOATInteractive Water Loss Model | JOATInteractive Water Loss Model | JOATInteractive Water Loss Model | JOATInteractive Water Loss Model | JOATInteractive Water Loss Model | JOATInteractive Water Loss Model | JOATInteractive Water Loss Model | JOATInteractive Water Loss Model | JOATInteractive Water Loss Model | JOATInteractive Water Loss Model | JOATInteractive Water Loss Model | JOATInteractive Water Loss Model | JOATInteractive Water Loss Model | JOATInteractive Water Loss Model | JOATInteractive Water Loss Model | JOATInteractive Water Loss Model | JOATInteractive Water Loss Model | JOATInteractive Water Loss Model | JOATInteractive Water Loss Model | JOAT
0 of 32 faults resolved
Water lossLossPressure controlPressureEnergy efficiencyEnergyResolved by JOATResolved

Joat Ville is losing half of its water

Every day 161 278 kilolitres are put into supply and only half of that is billed. The rest leaks away, is used through a meter that does not work, or is taken illegally.

Faults are marked on the network below. Select one to see what it costs and how it is resolved, then apply the fix and watch the balance change.

Water lossWater lossPressure controlPressureEnergy efficiencyEnergyResolved by JOATResolved

Drag to move around the town, pinch or scroll to zoom, and use the district buttons to jump between areas.

Every fault in the model, and the JOAT service that resolves it

The model above is interactive. The same information is set out below in full, so it can be read without using the simulation.

Service connection leak

A leaking service connection between the main and the property boundary. Service connection leaks are the single largest component of real losses in most distribution systems, and they run continuously until somebody goes looking for them. Modelled at 37 200 kl/day across 12 locations.

Leak Detection Management

Distribution main leak

A leak on a buried distribution main. Losses on mains are large, invisible from the surface, and often run for months before anyone reports them. Modelled at 7 200 kl/day across 3 locations.

Leak Detection Management

Large leak on the bulk main

A large leak on the bulk transmission main between the reservoir and the network. Remote bulk pipelines are rarely inspected, so leaks, air valve failures and vandalism go unnoticed for long periods. Modelled at 2 400 kl/day.

Intelligent Bulk Pipeline Monitoring and Assessment

Reservoir overflow

The reservoir has no working level control, so it spills every night when demand falls away. Overflow water has already been abstracted, treated and pumped, and then it is lost entirely. Modelled at 2 800 kl/day.

Intelligent infrastructure and level instrumentation

Broken metered connection

The consumer meter has stopped registering or under registers badly. The water is delivered and used, but it is never billed, so it appears as an apparent loss rather than a leak. Modelled at 3 508 kl/day across 4 locations.

Meter Audits, Calibration and Sizing

Un metered connection

A connection that was never metered. The consumption is real and authorised, but nothing is measured, so nothing can be billed and the zone balance is wrong. Modelled at 698 kl/day across 2 locations.

Meter audit and revenue enhancement

Illegal connection

An unauthorised connection drawing straight off the main. It is unmeasured, unbilled, and usually badly made, so it leaks as well as steals. Modelled at 2 094 kl/day across 3 locations.

Non Revenue Water reduction

Inaccurate bulk meter

The reservoir outlet meter under registers. Every water balance built on it is wrong, so the losses are understated and the wrong interventions get funded. Modelled at 1 503 kl/day.

Flow measurement and bulk meter replacement

Non working pressure reducing valve

The valve has failed open, so the zone runs at full supply pressure day and night. Excess pressure drives every leak in the zone harder and pushes the burst rate up, which is why pressure is dealt with before chasing individual leaks. Present in 2 zones.

Pressure Management

Valve holding a single fixed pressure

The valve holds one outlet pressure around the clock, so the zone is over pressurised for most of the day and night. An advanced pilot valve and control logger let the system self learn the network and hold the minimum pressure that still serves customers. Present in 2 zones.

Advanced Pressure Management, the i2O solution

Pump station running at fixed speed

The booster pumps run flat out and throttle against a control valve. Energy is burned to create pressure that is then thrown away, and the resulting transients fatigue the network. Modelled at 5 520 kWh/day of avoidable energy.

Variable speed drive optimisation

Verified results behind the model

The town is illustrative. The method is not. JOAT has applied these interventions for utilities, municipalities and industrial clients for more than 18 years, in South Africa and internationally.

38 704 km

of mains worked on

1 762 546

connections worked on

145,7 Ml/day

in verified savings

On the City of Cape Town project, advanced pressure management delivered a 38% reduction in leakage, a 58% reduction in burst frequency, and extended asset life by more than five years. In eThekwini, the same approach saves 3,1 million litres of water every day and reduced mains burst repairs by 67%.

Ready to Talk?

Whether you are planning an NRW reduction programme or specifying instrumentation for a project, the right team is one enquiry away.